BHEL to set up first-of-its-kind facility that will allow India to develop efficient thermal plants

Bharat Heavy Electronics Limited (BHEL) is working on a project to establish a high-temperature turbine rotor test rig for efficient coal-based Thermal Power Plants
BHEL to set up first-of-its-kind facility that will allow India to develop efficient thermal plants
  • Project taken up under Clean Energy Research Initiative of DST

  • It will be the first facility in India for experimental validation of the design of AUSC steam turbine rotor

New Delhi: India may soon manufacture its own super alloy steam turbine rotors for efficient coal-based thermal power plants. To execute this, a facility is being set up by Maharatna PSU, Bharat Heavy Electricals Limited (BHEL) to assess low cycle fatigue effects in rotors required for such power plants.

Improving technologies to increase the efficiency of coal-based thermal power plants requires the use of nickel-based super-alloy materials as against chrome-based steels widely used now. The nickel-based Alloy 617M has been selected by the Indian Advanced Ultra Super Critical (AUSC) consortium. The alloy is industrially available and the AUSC consortium has already expressed confidence in indigenous development of the alloy. However, lack of experimental data on the performance of Alloy 617M rotors hinders effective usage of this alloy in the Indian AUSC power plant.

To overcome this challenge, the Department of Science & Technology (DST) under the Clean Energy Research Initiative has supported a project to BHEL's (R&D), Hyderabad for the establishment of a High-Temperature Spin Test Rig (HTSTR).

It will be the first facility in India for experimental validation of the design of AUSC steam turbine rotor relating to creep-fatigue damage (deterioration of metals and alloys subjected to a cyclic thermomechanical load at elevated temperature) and will also be the only one of its kind in India in terms of establishing a real size engineering experimental set-up. It will subject the turbine rotor segments of weight up-to 9,000 kilograms to various damage conditions similar to that in the plant operation, like high temperatures up-to 800-degree celsius, high-speed up-to 3,600 Revolutions Per Minute (RPM), followed by long term steady-state operation and controlled heating and cooling. The facility will pave the way towards Atmanirbhar Bharat in this sector.

This facility will enable design validation of 800 Megawatts AUSC steam Turbine rotors for certifying the long term performance of superalloy Monometallic and Bimetallic welded rotor with a total of 2,000 startups (Hot+warm+cold) and 100,000 hours of total steady-state operation. This is achieved through accelerated testing within 200 cycles and 10000 hours, respectively. A unique test protocol for accelerated testing is formulated by the BHEL team with the guidelines of ASME standards. Two rotor segments – Monometallic (Alloy 617M) and Bimetallic welded portions (Alloy 617M and 10 Chrome) of actual steam turbine rotor will be subjected to equivalent operating conditions over its guaranteed timeline by increasing the temperatures and achieving desired thermal gradients within the rotors, during the heating and cooling operations.

This unique test protocol and its visualisation software are registered under Indian patents and copyrights act. Some of the technical highlights in the test methodology are published in National Conferences.

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Telegram. Join PSU Watch Channel in your Telegram and stay updated)