Highway construction slows to 20.43 km/day during Apr-Jul: Govt

The pace of national highway construction in the country has slowed to 20.43 km a day during the first four month of the current financial year

PSU Watch Bureau

New Delhi: The pace of national highway construction in the country has slowed to 20.43 km a day during the first four month of the current financial year, according to official data.

While the pace of national highway (NH) construction in the country had touched a record 37 km per day in 2020-21, it had slowed to 28.64 km a day in 2021-22, due to COVID-19 pandemic-related disruptions and a longer-than-usual monsoon in some parts of the country.

"The ministry has constructed 2,493 km of National Highways up to July in 2022-23, as compared to 2,927 km constructed up to July 2021-22," the Ministry of Road Transport and Highways (MoRTH) said in its monthly summary for the Cabinet for July 2022.

According to the ministry data, only 1,975 km of road projects were awarded between April-July in 2022, compared to 2,434 km of road projects awarded in the year-ago period.

The National Highways Authority of India (NHAI) and National Highways and Infrastructure Development Corporation Ltd (NHIDCL) are primarily responsible for the construction of national highways and expressways across the country.

The official target of highway construction has been kept at 12,000 km for the current financial year.

The ministry had constructed 10,237 km in 2019-20, 13,327 km in 2020-21 and 10,457 km in 2021-22.

(With PTI inputs)

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Google News. Click here to follow. Also, join PSU Watch Channel in your Telegram. You may also follow us on Twitter here and stay updated.)

PESB selects Rajeev Kumar Sinha and Nripendra Nath for Director (Technical) positions at CMPDIL

MOIL achieves record-breaking production in April–June quarter of FY 2025-26

NBCC signs MoU with NFDC for redevelopment of Siri Fort Auditorium complex

Stock markets climb in early trade amid optimism over India-US trade deal

Need to ensure washed coal replaces imported coal in coastal ICB power plants: MCL CMD