NTPC’s Kayamkulam floating solar power project becomes functional

Synopsis: NTPC Limited has declared the first part capacity of 22 MW out of 92 MW Kayamkulam floating solar power project in Kerala commercially operational. The floating solar system is being set up on the lake adjacent to NTPC's Rajiv Gandhi Combined Cycle Power Project (RGCCPP)

PSU Watch Bureau
  • KSEB is expected to start purchasing power from the floating solar power project in Kayamkulam at Rs 3.16 per unit soon
  • NTPC also declared 250 MW captive power unit of NTPC Sail Power Company Limited in Odisha commercially operational

New Delhi: State-run NTPC Limited has declared the first part capacity of 22 MW out of 92 MW Kayamkulam floating solar power project in Kerala commercially operational on Friday. "Consequent upon successful commissioning, first part capacity of 22 MW out of 92 MW Kayamkulam Floating Solar PV Project at Kayamkulam, Kerala, is declared on Commercial Operation w.e.f. 13:00 Hrs. of 31.03.2022," said NTPC in a regulatory filing on Friday. 

NTPC's Kayamkulam floating solar power project was to become operational in 2021. However, work was impacted due to delay in importing solar cells from China. The floating solar system is being set up on the lake adjacent to NTPC's Rajiv Gandhi Combined Cycle Power Project (RGCCPP). KSEB is expected to start purchasing power from the floating solar station at Rs 3.16 per unit soon. An agreement to this effect was signed between KSEB and NTPC a few years ago.

NTPC Ltd has doubled its renewable energy (RE) target for 2032 from 32 GW to 60 GW of solar and wind power. 

NTPC commissions 250 MW captive power unit in Odisha

In a separate regulatory filing to the stock exchanges on Friday, NTPC also declared 250 MW captive power unit of NTPC Sail Power Company Limited in Odisha commercially operational. "Consequent upon successful commissioning and due approvals, 250 MW Captive Power Unit, at Rourkela in the state of Odisha, of NTPC Sail Power Company Limited (a Joint Venture Company of NTPC Limited), is declared on Commercial Operation w.e.f. 00:00 hrs. of 29.03.2022," said the filing.

"With this, the installed and commercial capacity of NSPCL has become 1,064 MW while the group installed and commercial capacity of NTPC has become 68881.68 and 68221.68 MW, respectively," said the PSU.

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Google News. Click here to follow. Also, join PSU Watch Channel in your Telegram. You may also follow us on Twitter here and stay updated.)

MIDHANI is looking to hire Director (Finance); apply before Dec 2

Haryana CM Nayab Saini discusses power issues with HERC Chairman

Think out of the box, adapt to changing tech landscape: CAG tells officers

HPCL partners with The Akshaya Patra Foundation to feed 1000 school children for a year

DVC signs PPA with GUVNL, to supply 559 MW of electricity