Steel girders: Delhi Metro adopts unconventional construction on pink line

Delhi Metro adopted a unique construction method by using steel girders instead of the conventional concrete ones to complete civil work on the pink line

PSU Watch Bureau

New Delhi: To expedite work on the Trilokpuri section of Pink Line, the Delhi Metro adopted a unique construction method by using steel girders instead of the conventional concrete ones. The construction of concrete girders would have required the establishment of a casting yard and it would not have been feasible to set up a casting yard for such a small stretch within a short duration of time. Therefore, steel girders were installed on this stretch.

According to DMRC, a total of 40 steel girders have been placed on 10 spans for the 290 metre-long section. These steel girders have been fabricated and brought from a workshop at Ambala in Haryana. This has not only saved time but also there was no need to create a separate casting yard for the concrete casting of the girders.

The length of these girders varies from 16 to 38 metres. The height of the viaduct stands at about 8 to 9.5 metres. A curved span of radius 200 metres is also a part of this stretch. Earlier, for the construction of the Chhattarpur Metro station also, DMRC had adopted a similar method of using steel structures because the construction of that station was also delayed due to land acquisition issues.

The work on installing these steel girders and casting of deck slab was completed in April just before the second surge of the COVID-19 pandemic. This was a significant achievement because the civil construction on this stretch was started in early 2020 and was repeatedly hampered by the pandemic induced lockdowns and issues such as the non-availability of the workforce. Now, track laying and other ancillary works have commenced on this stretch between Mayur Vihar Pocket – 1 and Trilokpuri Sanjay Lake following the completion of civil work. In addition, overhead electrification work is also in progress.

ALSO READ:

The track laying work is expected to be completed by the end of June. Preliminary trials are expected to start thereafter. All efforts are being made to further expedite the progress of work on this particular stretch. The section shall be operational immediately after receiving the mandatory clearances from all concerned authorities.

Once completed, this section will connect the two ends of Pink Line and will provide seamless connectivity to a long range of localities in the national capital region (NCR). Important transport hubs such as Nizamuddin Railway Station, Sarai Kale Khan ISBT, Anand Vihar Railway Station, Anand Vihar ISBT, Delhi Cantt. Railway Station, and prominent markets like Dilli Haat – INA, Sarojini Nagar and Lajpat Nagar will get direct connectivity through this corridor.

This corridor will further be extended from Majlis Park to Maujpur in Phase – IV, making it the longest single Metro corridor in India at approximately 70 kilometers. After completion of Phase – IV, the Pink Line will also become the only Ring Corridor of Metro in the country.

DMRC is also developing an internal road below the viaduct at Trilokpuri which will connect the Vasundhara Road and Trilokpuri Road. The road will be 140 metres in length. This will help in decongesting the area and will ease the traffic scenario.

While the presently operational sections of the Pink Line were made functional in 2019, this small stretch got delayed due to the unavailability of encumbrance free land. After following the due process of law, the land was acquired and R&R (Rehabilitation and Resettlement) of Project Affected Persons was done for commencement and completion of construction work.

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Google News. Click here to follow. Also, join PSU Watch Channel in your Telegram. You may also follow us on Twitter here and stay updated.)

IIFCL in talks with ADB, Korean Exim Bank to raise $600 million

Govt notifies telecom cyber security rules; sets timelines for telcos to report security incidents

Govt invites job applications for PNGRB's Member post

Power Minister visits NHPC’s Nimoo Bazgo Power Station in Ladakh

Delegates from 18 countries attend RBI's policy conference of Global South central banks