NTPC’s 1,320 MW Tanda STPS Stage-II is set to be fully operational as the second unit of the power station is going to start commercial operations on July 1

PSU Watch Bureau
  • The Stage-II of NTPC's Tanda STPS has two units of 660 MW each
  • Unit-2 of NTPC's Barauni Thermal Power Station (TPS), Stage-II, has completed its trial operation successfully, said NTPC in separate news

New Delhi: NTPC Limited's UP-based 1,320 MW Tanda Super Thermal Power Station (STPS) Stage-II is set to be fully operational as the second unit of the power station is going to start commercial operations on July 1. In a regulatory filing to the stock exchanges on Monday, NTPC said, "… we wish to inform that Unit-2 of 660 MW capacity of Tanda Super Thermal Power Station, Stage-II (2 x 660 MW) is hereby declared on commercial operation w.e.f 00:00 Hrs of 01.07.2021."

PSU Watch had earlier reported that the Unit-2 of Tanda STPS Stage-II had completed its trial run successfully on April 5. The Stage-II of the STPS has two units of 660 MW each. 

Unit-2 of NTPC's Barauni TPS, Stage-II, completes trial run

In a separate regulatory filing, NTPC said that the Unit-2 of its Barauni Thermal Power Station (TPS), Stage-II, in Bihar has completed its trial operation successfully. "… we wish to inform that based on achievement of approved norms and due approvals, 2nd Unit of 250 MW capacity of Barauni Thermal Power Station, Stage-II (2 x 250 MW) has successfully completed trial operation and consequently included in the installed capacity of NTPC," said the filing.

ALSO READ

With this, the total installed capacity of NTPC and NTPC group has become 52,650 MW and 66,075 MW, respectively, said NTPC.

The backdrop

This is the second thermal power capacity addition announced by NTPC in 2021 after it said in January that its Meja Thermal Power Project became fully operational on January 31 with the Unit-II commencing commercial operation. Meja Thermal Power Project is a coal-based thermal power plant located in Meja Tehsil in Allahabad district, Uttar Pradesh. The planned capacity of the power plant is 1,320 MW (2x660MW).

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Google News. Click here to follow. Also, join PSU Watch Channel in your Telegram. You may also follow us on Twitter here and stay updated.)

IIFCL in talks with ADB, Korean Exim Bank to raise $600 million

Govt notifies telecom cyber security rules; sets timelines for telcos to report security incidents

Govt invites job applications for PNGRB's Member post

Power Minister visits NHPC’s Nimoo Bazgo Power Station in Ladakh

Delegates from 18 countries attend RBI's policy conference of Global South central banks