2 hydro projects in NE near completion, 3 others below 10% progress: Ministry data Image for representation only
News Updates

2 hydro projects in NE near completion, 3 others below 10% progress: Ministry data

Two of six hydro projects under construction in the North East are near done; three sit below 10% progress, against a 2030 deadline

EW Bureau

New Delhi: Two of the six hydroelectric projects under construction in the North Eastern Region — the 1,000 MW Subansiri Lower and Assam's 120 MW Lower Kopili — are near completion at over 97 percent physical progress, while three others remain below 10 percent, data the Ministry of Power placed in the Rajya Sabha on Monday shows.

The six projects, with a combined installed capacity of 2,166 MW, are all scheduled to be commissioned on or before December 31, 2030, according to the written reply by Minister of State for Power Shripad Naik, which gave physical progress as on June 30 this year.

A wide spread against a common deadline

The reply showed the projects clustered at the two ends of the progress scale. Alongside Subansiri Lower (97.84 percent) and Lower Kopili (98.65 percent), Sikkim's 120 MW Rangit-IV was at 97.34 percent and the 500 MW Teesta Stage VI at 73.48 percent. At the other end, three projects had barely begun: the 240 MW HEO and 186 MW Tato-I, both in Arunachal Pradesh, stood at 6.33 percent and 5.10 percent respectively, leaving a large share of capacity to be built in the roughly four and a half years to the December 2030 deadline.

By capacity, the projects span three states. Arunachal Pradesh accounts for the largest share at 1,426 MW across three projects — Subansiri Lower (which straddles the Arunachal-Assam border, in Lower Subansiri and Dhemaji districts), HEO and Tato-I. Sikkim has two, Teesta Stage VI and Rangit-IV, totalling 620 MW. Assam has one, Lower Kopili in Dima Hasao and Karbi Anglong districts, at 120 MW.

Follow PSU Watch on LinkedIN

NHPC, NEEPCO and APGCL executing

The projects are being built by three state-owned agencies, the reply said. NHPC is executing Subansiri Lower, Teesta Stage VI and Rangit-IV; NEEPCO is building HEO and Tato-I; and Assam Power Generation Corporation (APGCL) is executing Lower Kopili. The two projects furthest from completion, HEO and Tato-I, are both NEEPCO projects.

Assam's demand rising toward 2030

The projects are coming up as electricity demand in the region climbs. For Assam, the same reply projected peak demand rising to 3,403 MW by FY2029-30 from an estimated 2,914 MW in FY2026-27, and energy requirement to 18,162 million units from 14,978 million units over the same period, based on the midterm review of the 20th Electric Power Survey. In the current year up to June 2026, Assam met 2,658 MW of a 2,683 MW peak, the reply said, a shortfall of about 25 MW.

(PSU Watch is India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy. 👉 Click to join our channel now: PSUWatch WhatsApp Channel. Prefer LinkedIn? Follow PSU Watch on LinkedIN. Click to stay connected on Twitter here and stay updated)

AI data centres to add 26.3 GW of power load by 2031-32, to be served mainly by renewables: Naik

12.7 GWh of battery storage awarded, 0.5 GWh commissioned under budgetary VGF scheme: Naik

NABARD signs MoU with Maharashtra's MAHAPREIT to finance rural green infrastructure

Coal India board approves investment in rights issue of renewable JV CRAUL

Punjab CM Mann lays foundation for Rs 1,116 crore forging unit in Ludhiana