BCGCL floats tender for coal gasification project in Odisha 
News Updates

BCGCL floats tender for coal gasification project in Odisha

BCGCL has floated a tender document for the selection of LSTK-2 contractor for ‘Coal to Ammonium Nitrate’ Project at Odisha

PSU Watch Bureau

New Delhi: Bharat Coal Gasification & Chemicals Limited (BCGCL), a joint venture company of Coal India Limited (CIL) and Bharat Heavy Electricals Limited (BHEL), has floated a tender document for the selection of LSTK-2 contractor for ‘Coal to Ammonium Nitrate’ Project at Odisha on Thursday. The tender is available with tender number, PNMM/PC288/E/001, and the tender title, "Bharat Coal Gasification and Chemicals Limited, BCGCL,” on CPP portal. The LSTK-2 tender deals with Syngas Purification Plant and ammonia Synthesis gas plant that will purify the raw syngas produced from the coal gasifier and make it suitable for ammonia synthesis.

PSU Watch is now on Whatsapp Channels. Click here to join

The date for pre-bid has been scheduled on June 28 and interested bidders can share their queries by June 21.

CIL, BHEL to set up India's first commercial-scale coal gasification plant

CIL and BHEL have entered into an agreement for setting up India’s first commercial-scale coal-to-ammonium nitrate plant through surface coal gasification (SCG) technology route. As per the agreement, the gasification plant will be based on locally-developed coal gasification technology by BHEL, which utilised the high ash coal from Lakhanpur Area to produce 0.66 million metric tons per annum (MMTPA) of technical grade ammonium nitrate. The entire project cost, according to PFR, is Rs 11,782 crore. For the task of "Preparation of Detailed Feasibility Report (DFR)," M/s PDIL has been designated as PMC for the project.

CIL and BHEL have incorporated a joint venture company, BCGCL (CIN U23935OD2024GOI045884) on May 21, which marks the foray of these two PSUs into coal-to-chemical business. BCGCL is a subsidiary of Coal India in which CIL holds 51 percent and BHEL holds 49 percent equity.

The packaging philosophy for the execution of the project has been finalised as partial LSTK mode wherein four LSTK packages and 29 other offsites and utilities packages that will be done on EPC mode have been identified. Out of four LSTK packages, three packages namely LSTK-2, LSTK-3 and LSTK-4 will be executed through tendering route and remaining LSTK-1 will be done by BHEL on nomination basis.

LSTK packages

  • LSTK-1 Package: Coal Gasification, Air Separation Unit (ASU), Ash Handling Plan (AHP), Steam Generation Plan (SGP), Coal handling plant (CHP), Cooling Towers for Coal gasification

  • LSTK-2 Package: Raw Gas Purification including CO Shift Unit, Rectisol Unit, Sulphur Recovery Unit and Liquid Nitrogen wash Unit.

  • LSTK-3Package: Ammonia Synthesis Unit. Selection of EPC Contractor through tendering. 

  • LSTK-4 Package: Nitric Acid, Ammonium Nitrate Plant along with Prilling Tower along with Cooling Tower for Ammonia Unit, Nitric Acid Unit, Ammonium Nitrate Unit..

  • Offsites & Utilities: Selection of EPC Contractor through tendering wherein 29 packages have been identified whose estimate value will be taken for finalization of DFR.

The project has been envisaged in such a manner that no stone is left untouched, a land of around 350 acre is readily available with the CIL and off-take of the final product Ammonium Nitrate will be done by CIL and will be used in explosive activity for mining of coal. This will be the first commercial coal gasification plant that will showcase the indigenous coal gasification technology developed by BHEL. The Ministry of Coal launched the financial support/incentive/grant scheme to promote coal/lignite gasification projects of government PSUs and the private sector. The financial incentive up for offer under the scheme is divided into three categories. The project is expected to be the first to qualify for the benefit of Rs 1,350 crores under Category-1.

Additionally, tenders for LSTK- 3 and LSTK-4 have also been prepared and are under approval at CIL and it is expected that tenders for LSTK-3 and LSTK-4 will be floated as soon as possible.

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Google News. Click here to follow. Also, join PSU Watch Channel in your Telegram. You may also follow us on Twitter here and stay updated.)

IIFCL in talks with ADB, Korean Exim Bank to raise $600 million

Govt notifies telecom cyber security rules; sets timelines for telcos to report security incidents

Govt invites job applications for PNGRB's Member post

Power Minister visits NHPC’s Nimoo Bazgo Power Station in Ladakh

Delegates from 18 countries attend RBI's policy conference of Global South central banks