Cabinet approves two corridors under Delhi Metro Phase-IV 
News Updates

Cabinet approves two corridors under Delhi Metro Phase-IV

The Union Cabinet on Wednesday approved two new corridors of Delhi Metro's Phase-IV project in a move that will further improve the metro connectivity in the national capital

PTI

New Delhi: The Union Cabinet on Wednesday approved two new corridors of Delhi Metro's Phase-IV project, Lajpat Nagar to Saket G-Block and Inderlok to Indraprastha, in a move that will further improve the metro connectivity in the national capital.

According to an official statement, the total project cost of these two corridors is Rs 8,399 crore, which will be sourced from the Centre, Delhi government and international funding agencies.

PSU Watch is now on Whatsapp Channels. Click here to join

The Cabinet chaired by Prime Minister Narendra Modi approved the new corridors, to be completed by March 2026 in stages.

At a press briefing after the cabinet meeting, Union minister Anurag Thakur said that with the new corridors, the national capital region will have a total Metro network of around 450 km as against the present 427 km.

Of the total expenditure of Rs 8400 crore for the two new corridors, the minister said, the Government of India will spend Rs 1,547 crore, the Delhi government will spend Rs 1,987 crore, Rs 4,309 crore will come from JICA as loan, Rs 333 crore from internal accruals of DMRC and Rs 195 crore through PPP component.

Once complete, he said, a total of 2.5 lakh people will travel in these lines. A total of 65-70 lakh people travel through the metro network in Delhi currently.

The statement stated that these two lines will have a combined length of 20.762 km. The Inderlok-Indraprastha corridor will be an extension of the Green Line and will provide interchange with the Red, Yellow, Magenta, Violet and Blue Lines and Airport Line, while the Lajpat Nagar-Saket G Block corridor will connect the Silver, Magenta, Pink and Violet Lines.

The Lajpat Nagar-Saket G Block corridor will be entirely elevated and will have eight stations. The Inderlok-Indraprastha corridor will have 11.349 km of underground lines and 1.028 km of elevated lines with 10 stations.

"The Inderlok-Indraprastha Line will provide enhanced connectivity to the Bahadurgarh region of Haryana as commuters from these areas will be able to travel on the Green Line to directly reach Indraprastha as well as various other areas of central and east Delhi," the government said in the statement.

Eight new interchange stations will come up on these corridors at Inderlok, Nabi Karim, New Delhi, Delhi Gate, Indraprastha, Lajpat Nagar, Chirag Dilli and Saket G Block. These stations will significantly improve inter-connectivity among all the operational lines of the Delhi Metro network, it stated.

The Delhi Metro is already constructing a network of 65 km as part of its fourth phase of expansion.

Currently, the DMRC operates a network of 391 km consisting of 286 stations. The Delhi Metro is now one of the fastest growing networks in the world.

The Delhi Metro Rail Corporation Limited (DMRC) has already started the pre-bid activities and preparation of tender documents.

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Google News. Click here to follow. Also, join PSU Watch Channel in your Telegram. You may also follow us on Twitter here and stay updated.)

IIFCL in talks with ADB, Korean Exim Bank to raise $600 million

Govt notifies telecom cyber security rules; sets timelines for telcos to report security incidents

Govt invites job applications for PNGRB's Member post

Power Minister visits NHPC’s Nimoo Bazgo Power Station in Ladakh

Delegates from 18 countries attend RBI's policy conference of Global South central banks