News Updates

L&T finishes Cryostat order for world’s largest nuclear fusion project before schedule

L&T has flagged-off the most complex and final assembly of Cryostat for the world’s largest nuclear fusion project in France ahead of schedule

PSU Watch Bureau
  • With the supply of the top lid sector, we have successfully completed our India scope of the project ahead of the schedule, said Anil V Parab, L&T Heavy Engineering

  • The Cryostat assembly referred to as the Top Lid, weighing 650 MT, is to be installed with other Cryostat segments for ITER in a reactor pit in southern France

Hazira (Gujarat): The heavy engineering arm of L&T has flagged-off the most complex and final assembly of Cryostat — the largest stainless-steel, high-vacuum pressure chamber in the world — for the world's largest nuclear fusion project in France. "This is an important milestone in the global nuclear fusion arena as well as a moment of pride for the Make in India initiative," L&T said in an official release on Tuesday. Commenting on the news, Dr. Bernard Bigot, Director-General, ITER (International Thermonuclear Experimental Reactor) organisation said, "Today, in Hazira, we celebrate with you the completion of fabrication of all the segments of the Cryostat, including most recently, the segments of the Cryostat Lid — again achieved under these challenging conditions. The ITER Project and ITER-India were very fortunate to have L&T as our partner and the primary contractor for Cryostat fabrication… (as) the challenge of the Cryostat was unique."

SN Subrahmanyan, CEO and MD L&T, said, "This is a proud moment for the company, as it has completed another milestone in the development of the world's largest stainless-steel, high-vacuum pressure chamber. The company has used innovative and digital manufacturing techniques to ensure uninterrupted supply of high quality, high-precision assemblies to ITER. This will further pave the way for the installation of Cryostat at the project site in France and eventually lead to the demonstration of large-scale feasibility of fusion power. It has empowered India to tread towards Aatmanirbhar Bharat by acquiring knowledge in this highly specialised field of science and technology."

The Cryostat assembly referred to as the Top Lid, weighing 650 MT (metric tons), is to be installed with other Cryostat segments for ITER (International Thermonuclear Experimental Reactor) in a reactor pit in southern France. L&T has already delivered the base section, the lower cylinder and the upper cylinder for the Cryostat. The Cryostat's function is to provide cooling to the fusion reactor and to keep very high temperatures at its core under control.

'L&T Heavy Engineering showcasing Indian capabilities at global stage'

Anil V Parab, Executive Vice President and Head, L&T Heavy Engineering, said, "With the supply of the top lid sector, we have successfully completed our India scope of the project ahead of the schedule. The fabrication of these components has been an engineering marvel both in terms of its massive size and its stringent quality standards. This is a proud moment for L&T Heavy Engineering, which is showcasing Indian capabilities in the high technology arena at the global stage."

The project scope for L&T Heavy Engineering is divided into three aspects. Firstly, the company was to manufacture assemblies at its state-of-the-art Hazira manufacturing complex. The second aspect involved constructing a temporary workshop at the project site in Cadarache, France for the assembly of various sectors. And finally, it is to integrate the Cryostat with the Tokamak Reactor building. With this flag-off, L&T Heavy Engineering has completed the manufacturing work planned in India.

The backdrop

L&T's Heavy Engineering business won this prestigious contract from ITER India, a wing of Department of Atomic Energy, for the ambitious mega scientific project, conducted in collaboration with seven elite countries, including India, and with a project outlay of around $20 billion.

L&T Heavy Engineering has state-of-the-art, fully integrated, world-class manufacturing facilities at Hazira (Surat), Powai (Mumbai) and Vadodara. 

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Telegram. Join PSU Watch Channel in your Telegram and stay updated)

REC receives Adam Smith Awards ASIA 2024 for best funding solution

Mumbai Airport's total passenger traffic rises 4% in Oct

Oilfield amendment bill to provide policy stability: Puri

Nepal exports 40 MW power to Bangladesh for the first time

DVC awards EPC contract to BHEL for Koderma Thermal Power station phase-II