MP and UP pioneer joint procurement of pumped storage Representative Image
News Updates

MP and UP pioneer joint procurement of pumped storage

MP and UP have pioneered a joint procurement model for pumped storage capacity based on their complementary seasonal electricity requirements, an official said on Wednesday

PSU Watch Bureau

New Delhi: Madhya Pradesh and Uttar Pradesh have pioneered a joint procurement model for pumped storage capacity based on their complementary seasonal electricity requirements, an official said on Wednesday.

The key feature of this model is the coordinated use of the same energy storage capacity in accordance with the seasonal variations in electricity demand in the two states, he said.

Follow The PSUWatch Channel on Whatsapp

Madhya Pradesh will utilise the storage capacity from November to April, while Uttar Pradesh will use it from May to October.

The Madhya Pradesh Power Management Company Limited (MPPMCL), in collaboration with Uttar Pradesh, has completed the procurement process for 500 MW of Pumped Storage Project (PSP) capacity through a competitive e-reverse auction.

The innovative arrangement is expected to optimise the utilisation of energy storage infrastructure throughout the year, reduce power procurement costs and minimise the need for separate investments in storage capacity by the two states, the official said.

The arrangement will reduce the need for each state to independently establish additional energy storage capacity.

As part of the procurement process, a long-term Power Purchase Agreement (PPA) is proposed for 500 MW of capacity from pumped storage projects connected to the Inter-State Transmission System (ISTS). The proposed agreement will have a tenure of 40 years, with an energy storage duration of six hours and provision for continuous power supply for up to four hours, the official said.

Follow PSU Watch on LinkedIN

Following a competitive e-reverse auction lasting four hours, the lowest discovered rate (L1) stood at Rs 1.3487 crore per MW per year, inclusive of the cost of cycle losses. According to MPPMCL, this rate is significantly lower than those recently discovered for comparable pumped storage projects in the country.

The arrangement is also expected to reduce dependence on expensive short-term power purchases during periods of peak demand.

This could serve as a useful model for other states too, the official added.

(PSU Watch is India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy. 👉 Click to join our channel now: PSUWatch WhatsApp Channel. Prefer LinkedIn? Follow PSU Watch on LinkedIN. Click to stay connected on Twitter here and stay updated)

Wipe out drug menace, prevent Naxalism's return: PM Modi at Council of Ministers meet

India's challenge next year may be rupee strength, not weakness: CEA

Capital market players seek cut in capital gains, transaction tax in Budget FY28

Vedanta Group explores using AI in complex mineral production

India on track to hit $1 trillion in exports this year: Commerce Secretary