NHPC defers full commissioning of 300 MW Bikaner solar project by a month File Photo
News Updates

NHPC defers full commissioning of 300 MW Bikaner solar project by a month

NHPC says full commissioning of its 300 MW Bikaner solar project is now expected by Sept 30, with 214 MW already operational

EW Bureau

New Delhi: State-run hydropower major NHPC Ltd has informed the stock exchanges that the full commissioning of its 300 MW Karnisar Solar Power Project in Bikaner, Rajasthan, will be delayed by a month.

PSU Watch is now on Whatsapp Channels. Click here to join

In its filing, NHPC said that out of the total planned 300 MW capacity, 214.28 MW has already been commissioned. The project, which is part of NHPC’s renewable energy expansion, is designed as a grid-connected solar PV installation.

Remaining capacity to come online in September

According to the company, the balance capacity is now expected to be commissioned by September 30, instead of August 31, as previously indicated. The disclosure was made under Regulation 30 of SEBI’s Listing Obligations and Disclosure Requirements (LODR) Regulations, 2015.

The Karnisar project forms a crucial part of NHPC’s broader push into solar and wind energy, as it looks to diversify beyond its traditional hydropower base and contribute to India’s clean energy targets.

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Google News. Click here to follow. Also, join PSU Watch Channel in your Telegram. You may also follow us on Twitter here and stay updated.)

Coal India Q1 profit stays flat as rising input costs erode 8% revenue gain; board declares Rs 5.50 interim dividend

NHPC appoints Paresh Rasiklal Ranpara as Director (Personnel)

Keshav Chandra (IAS) assumed charge as Secretary of Ministry of Mines

BCCL offers 50 internships opportunities under PM Internship Scheme

BEL Q1 net profit rises 8% to Rs 1,048 crore; revenue jumps 25%