THDC aims to make Rs 12,000 crore coal-based thermal power project operational by Sept 2024 
News Updates

THDC aims to make Rs 12,000 crore coal-based thermal power project operational by Sept

THDC India says that it aims to make its coal-based power plant operational by September 2024

PTI

New Delhi: THDC India Ltd aims to make its coal-based power plant operational by September 2024, marking an entry into the domestic thermal energy sector, a top company official said.

PSU Watch is now on Whatsapp Channels. Click here to join

THDC is setting up a 1,320 Megawatt (2X660 MW) Super Thermal Power Project (STPP) at Bulandshahr district in Uttar Pradesh (UP), the official said in reply to a query about the company's plans of setting up coal-based capacities.

At present, the Uttarakhand-based entity has an installed power generation capacity of around 1,587 MW, of which 1,424 MW is hydro, 113 MW wind and 50 MW solar.

When asked about the timeline of the project, the official said, "The work is going on in full swing. We are confident of making the first unit of 660 MW operational by September this year and the second unit operational by March 2025. It is a project of around Rs 12,000 crore."

Till January 2024, a sum of Rs 9,428.30 crore has been spent on the Khurja Super Thermal Power Plant (KSTPP), the company official said, adding that around 85 percent of the work has been completed.

The company is in the process of implementing a environment-friendly carbon capture technique at the Khurja STPP, which will capture the CO2 emissions, the official added.

Sharing the details of the project, the official further said the foundation stone for the project was laid by Prime Minister Narendra Modi on March 9, 2019. The project spreads over an area of 1,200.843 acres.

It is an integrated coal-based thermal power plant with linkage of operational Amelia coal mine located at Singrauli district, Madhya Pradesh, the official said.

Once completed, the plant will generate 9,264 million units (MUs) of power annually corresponding to 85 percent plant load factor (PLF).

As per allocation of power by the Ministry of Power, 64.7 percent of the power generated (854 MW) is to be supplied to UP and balance to other beneficiaries.

On the status of the project, the official said, "Recently, a milestone was achieved towards the commissioning of Khurja STPP with the engine rolling on railway siding (downline) from Danwar station to the plant yard. It will allow receiving coal rakes from Amelia coal mines to Khurja STPP through Danwar station."

Several other project related works like boiler light up of Unit 1, and aux boiler light up etc. have been achieved as per schedule, he added.

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Google News. Click here to follow. Also, join PSU Watch Channel in your Telegram. You may also follow us on Twitter here and stay updated.)

Avaada Group to invest Rs 5,800 crore in Rajasthan to develop RE projects

NTPC Green Energy IPO fully subscribed

Sensex, Nifty bounce back in early trade after sharp fall in previous session

These are the Central, state PSUs named in US court indictment in Adani bribery case

Gautam Adani bribery case: Allegations, rebuttals, stock market wipeout & all you want to know