Thermal plants had 33.5 MT of coal stock on Sunday, sufficient to run projects for 12 days: R K Singh 
News Updates

Thermal plants had 33.5 MT of coal stock on Sunday, sufficient to run projects for 12 days: R K Singh

Thermal power plants monitored by the CEA had 33.5 MTs of coal stock on Sunday, which was sufficient to run them for 12 days, said Singh

PSU Watch Bureau

New Delhi: Thermal power plants monitored by the Central Electricity Authority (CEA) had 33.5 million tonnes of coal stock on Sunday, which was sufficient to run them for 12 days at 85 percent capacity utilisation, Parliament was informed on Thursday. This assumes significance in view of projection of an unprecedented high demand of electricity during this summer. Electricity demand is expected to touch 229 GW next month as per power ministry estimates.

'Coal stock of 33.5 MTs was available on Sunday, sufficient for 12 days '

"As on March 12, the total coal stock available with coal-based thermal power plants monitored by CEA was 33.5 Million Tonne (MT), which was sufficient for an average of 12 days at a requirement of 85 percent Plant Load Factor (PLF)," Union Power Minister R K Singh said in a written reply to Lok Sabha.

'Coal based installation capacity stood at 51.27% on Jan 31'

In another reply to the House, Singh stated that as on January 31, coal (including lignite) based installed capacity was 51.27 percent of the total installed capacity.

The CEA has carried out generation expansion planning studies and published draft National Electricity Plan (NEP) in 2022 which reveals that the share of coal (including lignite) based capacity in the total installed capacity of the country is likely to reduce to 38.4 percent by March 2027 and to around 28.7 percent by March 2032, he added.

Studies also reveal that the share of coal-based generation is likely to reduce to 58.9 percent of the total generation mix by 2026-27 and to 49.9 percent by 2031-32 from 72.3 percent as of March 2022, he explained.

'211 hydroelectric projects under operation'

In another reply, Singh said, "At present, 211 hydroelectric projects (above 25 MW capacity), with an aggregate installed capacity of 46,850 MW are under operation in the country."

"41 hydroelectric projects (HEPs) totalling 17,803.5 MW are under implementation in the country. Of these, 32 HEPs totalling 16,567.5 MW are under active construction and nine projects totalling 1,236.0 MW are held up," he told the House.

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Google News. Click here to follow. Also, join PSU Watch Channel in your Telegram. You may also follow us on Twitter here and stay updated.)

REC receives Adam Smith Awards ASIA 2024 for best funding solution

Mumbai Airport's total passenger traffic rises 4% in Oct

Oilfield amendment bill to provide policy stability: Puri

Nepal exports 40 MW power to Bangladesh for the first time

DVC awards EPC contract to BHEL for Koderma Thermal Power station phase-II