BHEL bags Rs 1,600-cr order for Khurja power project

BHEL has bagged an order for Turbine Generator and associated packages for the greenfield 2x660 MW Khurja power project
BHEL bags Rs 1,600-cr order for Khurja power project

New Delhi: Amidst stiff international competitive bidding (ICB), Bharat Heavy Electricals Limited (BHEL) has bagged an order for Turbine Generator (TG) and associated packages for the greenfield 2×660 MW Khurja Super Thermal Power Project in Bulandshahr district of Uttar Pradesh (UP). Valued at around Rs 1,600 crores, the order for the Khurja power project has been placed on BHEL by THDC India Ltd, a joint venture of the government of India and the government of Uttar Pradesh.

BHEL's scope of work at Khurja power project

BHEL's scope of work in the contract includes design, engineering, manufacture, supply, erection, testing and commissioning of the TG and associated packages for the 2×660 MW Khurja power project.

"BHEL envisages indigenous manufacturing and sourcing of both the turbine-generator sets for this project, thereby providing impetus to the government's 'Make in India' initiative," a press release said.

Key equipment to be manufactured at Haridwar

The key equipment for the project will be manufactured at BHEL's Haridwar, Bhopal, Hyderabad, Jhansi, Trichy, Thirumayam and Bengaluru plants. The complete system engineering of the package will be carried out by the company's Project Engineering Management (PEM) division and the construction and installation activities on-site will be carried out by the company's Power Sector, Northern Region division, Noida, UP.

BHEL has contributed around 74 percent of the state's coal-based power generation capacity, aggregating to approximately 17,000 MW.

The backdrop

BHEL is the leading power equipment manufacturer with 58 sets of supercritical boilers and 53 sets of supercritical steam turbine generators ordered on it so far, by various customers in the domestic as well as overseas markets.

The company is India's largest manufacturer of power generation equipment with an installed base of over 1,85,000 MW of power plant equipment globally.