SJVN’s CMD triggers last blast for breakthrough in Naitwar Mori Hydro Electric Project

SJVN Limited CMD Nand Lal Sharma triggered the last blast for the breakthrough between Face-1 & Face-2 of 4.34 Kms long Head Race Tunnel of 60 MW Naitwar Mori Hydro Electric Project
SJVN’s CMD triggers last blast for breakthrough in Naitwar Mori Hydro Electric Project
Published on

New Delhi: SJVN Limited's Chairman & Managing Director (CMD) Nand Lal Sharma in presence of SJVN Limited's Director (Civil) SP Bansal, Director (Finance) AK Singh, Director (Electrical) Susheel and Project Head of 60 MW Naitwar Mori Hydro Electric Project (Uttarakhand) HR Thakur triggered the last blast for the breakthrough between Face-1 and Face-2 of Head Race Tunnel.

The Head Race Tunnel (HRT) which is 4.34 kms long with a diameter of 5.6 meters, 3.9 Kms of this HRT has already been excavated. The CMD along with Directors also visited the different project components and reviewed the progress in detail. Besides imparting guidance for critical areas, he exhorted the project officials and contractors to complete the project by December 2021.

On this occasion, Sharma told that the foundation stone of this project was laid by Union Minister of State (Independent Charge) Power RK Singh and Chief Minister of Uttarakhand Trivender Singh Rawat on March 30, 2018.

While speaking about the project, Sharma told that the dam structure of the project will be 30.5 m high and underground powerhouse will have two 30-MW vertical Francis turbines.

He further reiterated the resolve of team SJVN that the project will be commissioned in a "record period of 48 months." He also told that after the project is commissioned, 12 percent free electricity will be supplied to Uttarakhand as a royalty. In addition, each project-affected family will be provided with an amount equivalent to the cost of 100 units of electricity per month for ten years.

Sharma further said that Naitwar Mori has the potential to generate 265.5 million units of electricity every year. The estimated cost of the project, at the October 2016 price level, is around Rs 650 Crores.

SJVN is vigorously marching forward for achieving installed capacity of 5,000 MW by 2023, 12,000 MW by 2030 and 25,000 MW by the year 2040.

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Telegram. Join PSU Watch Channel in your Telegram and stay updated)

logo
PSU Watch
psuwatch.com