SJVN bags 5 hydro projects of 5097 MW in Arunachal Pradesh

The government of Arunachal Pradesh has allotted five projects of 5097 MW to SJVN Limited. All the allocated projects are situated in tributaries of Dibang River
SJVN bags 5 hydro projects of 5097 MW in Arunachal Pradesh
SJVN bags 5 hydro projects of 5097 MW in Arunachal Pradesh

New Delhi: The Government of Arunachal Pradesh has allotted five projects of 5097 MW to SJVN Limited. All the allocated projects are situated in tributaries of Dibang River. The allocated projects are 3097 MW Etalin, 680 MW Attunli, 500MW Emini, 420 Amulin and 400 MW Mihumdon.

SJVN's Chairman & Managing Director (CMD) NL Sharma informed that Government of Arunachal has terminated memorandums of agreement with various private power developers as they "showed less interest" in executing projects allotted to them. The projects which have been withdrawn from private developers are now being handed over to central public sector understandings.

SJVN bags 5 hydro projects of 5097 MW in Arunachal Pradesh
SJVN signs MoU with REC to secure Rs 50,000 crore for RE projects

Sharma said that 3097 MW Etalin and 680 MW Attunli were earlier allocated to private players as there was no physical progress in both the projects the projects are now have been allotted to SJVN. In addition to SJVN projects are also been allocated to other central public sector understandings namely NEEPCO, NHPC and THDC.

Sharma further apprised that Government of Arunachal Pradesh has considered his proposition of One Basin One Developer and allocated all the 5 projects in Dibang Basin, which will result in optimal resource utilisation and timely completion of projects. The development of these project will involve an investment of more than R 50,000 crores, while construction of these projects will reduce carbon emission in tune of around 1.1 million tonnes per year.

Lal further informed that agreement for the implementation of these projects will be signed soon in an event which will be graced by Chief Minister of Arunachal Pradesh, Pema Khandu and Union Power Minister RK Singh.

The portfolio of SJVN is now 55,527 MW. The company is on rapid progression to achieve its shared vision of being 25,000 MW company by 2030 and 50,000 MW by 2040. This shared Vision has been formulated in sync with the commitment of the government of India of generating 50 percent energy from non-fossil fuel-based energy resources by 2030.

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Google News. Click here to follow. Also, join PSU Watch Channel in your Telegram. You may also follow us on Twitter here and stay updated.)