Tata Power acquires Bikaner-Neemrana Transmission Project

Tata Power on Saturday said it has acquired Bikaner-Neemrana Transmission Project through a bidding process
Tata Power acquires Bikaner-Neemrana Transmission Project
Tata Power acquires Bikaner-Neemrana Transmission Projectfile

New Delhi: Tata Power on Saturday said it has acquired Bikaner-Neemrana Transmission Project through a bidding process.

Bikaner-III Neemrana-II Transmission Ltd is a special purpose vehicle (SPV) set up by PFC Consulting, for the project.

Public Sector's voice PSU Watch is now on Whatsapp Channels. Click here to join

The company has acquired Bikaner-Neemrana Transmission Project to boost renewable energy evacuation in India, a company statement said.

The company received the letter of intent (LOI) after emerging as a successful bidder in the Tariff-Based Competitive Bidding (TBCB) process, as per the guidelines issued by Ministry of Power, it added.

The project, which will be developed on a Build-Own-Operate-Transfer (BOOT) basis, will enable the evacuation of 7.7 GW of renewable energy from the Bikaner Complex in Rajasthan.

The project entails the establishment of a 340-km transmission corridor from Bikaner-III pooling station to Neemrana II substation.

Tata Power will maintain the transmission project for a period of 35 years. It is estimated to cost Rs 1,544 crore and is expected to be commissioned within 24 months from the date of transfer of the project SPV.

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Google News. Click here to follow. Also, join PSU Watch Channel in your Telegram. You may also follow us on Twitter here and stay updated.)

logo
PSU Watch
psuwatch.com