Delay in transmission infra bigger challenge for RE expansion than land availability: SECI MD PSU Watch
RE-INVEST

Delay in transmission infra bigger challenge for RE expansion than land availability: SECI MD

Shalini Sharma

Gandhinagar: State-run Solar Energy Corporation of India (SECI), a newly-minted Navratna public sector undertaking (PSU), is at the forefront of the expansion of Renewable Energy (RE) in India. SECI’s Managing Director (MD) RP Gupta spoke to PSU Watch on the sidelines of RE-Invest 2024 and discussed the challenges facing the next phase of RE expansion in India. He said that timely creation of RE power transmission infrastructure poses a bigger challenge for RE expansion than land availability because it is taking longer to put up transmission lines than set up RE projects. The SECI MD said that three geographical locations in India — the Great Rann of Kutch in Gujarat, the entire desert in Rajasthan and Ladakh — have enough chunks of land to meet India’s RE requirements well through 2047.

He also discussed SECI’s future growth strategy as it completes 13 years of its foundation on September 20. Here are excerpts:

The first phase of renewable energy expansion was about bringing down the tariff to a level to make solar power commercially viable. And we did bring it down to Rs 2-2.5/unit, making it cheaper than thermal power. As we undertake this next phase of expansion to reach the target of 500 GW of RE by 2030, what are the challenges that the sector will encounter next?

See, the major challenges, in my opinion, are two. One is transmission. Transmission infrastructure is unable to keep pace with the growth of renewables. Transmission is still aligned with the old thermal power system where the power plant took four-to-five years to come up. However, this is green energy. The projects here are completed very fast. They take roughly about two years or so. So, timely creation of transmission infrastructure is becoming a major constraint for us.

The second problem that the renewable energy sector faces is land availability. Particularly, suitable land availability. There is plenty of land available. But finding land where there is potential for RE generation is a problem. But of late, we have discovered new areas. For example, the Great Rann of Kutch here in Gujarat. The whole desert of Rajasthan. The area of Ladakh. These are all areas which are most suitable for renewable energy. And fortunately, there are no habitations over there. They have sparse population and they cannot be put to any other use. So, these areas are very huge chunks of land and are in a position to fulfill our renewable energy needs for as long as 2047.

SECI has worked out a variety of arrangements in its tenders for RTC power, for integrating battery energy storage, for integrating thermal power with solar power. What are the other innovative ways in which SECI is planning to meet the requirement of RTC power?

See, what we do is we try to assess the requirement of DISCOMs (power distribution companies). We essentially look at how we can couple a number of things to make a much more stable energy available to DISCOMs at the cheapest price. There is a fundamental difference between thermal energy and renewable energy. Thermal energy you can provide on demand, whereas, renewable energy can’t be provided on demand. You can provide it as and when it is available. So, the new system requirement is of storage. But that increases the cost. So, our whole endeavour is about how we can bring down the cost of energy. That is why all the new products, whether it is RTC, hybrid, peak power, FDRE, or battery and solar energy, we assess the requirements of DISCOMs and act accordingly.

What is the cheapest tariff that SECI has discovered for battery energy storage and RTC power?

Just a day ago, we completed our tender for battery energy storage and the rates which we have got are at par with what the Gujarat government has got. We have got slightly higher rates. Gujarat got Rs 3.76 lakh per MW per month. Whereas, we have got Rs 3.81 lakh per megawatt per month. That is a difference of about Rs 5,000 per MW. But the difference is Gujarat is providing land. We are asking the successful bidder to arrange the land.

There are many RE projects where PPAs and PSAs have not been signed yet. What are the challenges here?

Actually, the problem is that we have suddenly increased our capacity addition from roughly 15 GW of RE to 50 GW a year. Now, we cannot expect that states are in a position to absorb that kind of energy immediately. However, the necessity to meet RPO targets is gradually sinking in and states are realising that they can no longer be aloof. RPO targets are with them and if they do not comply, there will be penalty. So, as states are realising it, PPAs are getting signed. So, it is a temporary hiccup. These will be signed very quickly.

About 15 GW of RE projects are yet to sign PPAs and 14 GW are awaiting the signing of PSAs, which totals to 29 GW. Are these figures correct?

That figure is not to be read together, combined. PPAs or PSAs have not been signed for about 15 to 20 GW, not 29 GW. So, the 15-20 GW figure is an overall figure for which PPAs or PSAs are yet to be signed. But these will be done soon.

The growth of RE capacity installation is happening at a great pace but the integration of RE power into the grid is still very small. By when do you see the grid getting decarbonised at pace with RE capacity addition?

See, I would say both RE generation and RE integration into the grid cannot come until transmission and evacuation facilities are available. So, these are delayed. Our projects are also delayed because of delays in transmission systems.

Also, with the quantum of renewable energy getting into the grid, battery is one of the requirements and we are bringing in the battery component as well. I would not say battery, but the storage component. Battery happens to be the cheapest storage component. Currently, the renewables comprise roughly about 23 to 24 percent of the total generation. By 2030, it is supposed to reach about 45 percent as per the RPO trajectory, which will take care of roughly about 500 GW of renewable energy that we are planning to put in place by then.

What is the capacity that you are looking to bid out this year?

Roughly, 20 GW. And we will also be starting construction of our own RE projects. We hope to start about 1,200 MW of our own RE projects. In the next two years, they will be completed.

What about standalone battery storage tenders which states were very excited about?

For standalone battery storage, we have just recently completed a tender where I told you the rate we got. Yes, states have been very enthusiastic about it. But, going forward, I think we would prefer that states go for standalone battery systems on their own because the returns for SECI are very, very low. So, I would prefer that the state themselves do it. Unless the state asks us to do it, then we will of course do it. Because we don’t just look at returns. We are more of a facilitator of renewable energy.

SECI has also just floated its first tender for 500 MW offshore wind project. What is the timeline for closing this tender?

We hope to complete this tender in the next two months. We are waiting to see what kind of response we get from developers. Then the next 500 MW offshore wind project tender would also come for Tamil Nadu coast within this financial year. And we will aim to complete the second tender within this FY as well.

So, you are soon celebrating 13 years of your foundation. What are the targets or milestones that you hope to achieve in the time to come?

We have already become a Navratna company. No other company, no other PSU has been able to do it in such a short timeframe. Our growth is currently roughly about 30 percent per year in terms of PAT (Profit After Tax). This we hope to continue, not only continue but increase it further. How much we can do will depend on how innovative we are, how much we are able to take our stakeholders with us, but hopefully our growth should accelerate. An important development, going forward, would be that we will be changing the nature of our business. From currently just bidding out RE projects, we will be now putting up a lot of our own projects. Roughly, about 10 GW by 2035. Now we will be starting the process of participating in bids.

And we will also help C&I (Commercial & Industrial) customers to put up their own projects. So, we will be taking up PMC (Project Management Consultancy) work in a big way.

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Google News. Click here to follow. Also, join PSU Watch Channel in your Telegram. You may also follow us on Twitter here and stay updated.)

GeM slashes transaction charges levied on sellers, service providers for public procurement

India's coal mining methane emissions could more than double by 2029: Report

Markets rally in early trade tracking firm global peers

DVC followed all norms before releasing water from dams: Govt

EXCLUSIVE: SJVN to list its green arm before FY25-end, will look to raise Rs 3,000-4,000 cr: Director (Finance)