Sikkim landslide caused Rs 327 crore loss to Teesta-V project: NHPC 
News Updates

Sikkim landslide caused Rs 327 crore loss to Teesta-V project: NHPC

NHPC on Tuesday said a major landslide in Sikkim affected its 510 MW Teesta-V Power Station and the estimated loss was around Rs 327.67 crore

PTI

New Delhi: State-run hydro power giant NHPC Limited on Tuesday said a major landslide in Sikkim affected its 510 MW Teesta-V Power Station and the estimated loss was around Rs 327.67 crore.

PSU Watch is now on Whatsapp Channels. Click here to join

The power station is currently not operational and undergoing restoration works after flash flood of October, 2023, the company stated in regulatory filing.

The "estimated total amount of loss/ Re-do cost towards material damage (being intimated to insurance company) due to landslide at Teesta-V Power Station (510 MW) occurred on August 20, 2024 is Rs 327.67 crore."

Teesta-V Power Station (3x170 MW) is a run of the river scheme with diurnal storage to harness the hydro power potential of river Teesta for peaking during the lean season and is located in the state of Sikkim.

The power station was commissioned in 2008.

(PSU Watch– India's Business News centre that places the spotlight on PSUs, Bureaucracy, Defence and Public Policy is now on Google News. Click here to follow. Also, join PSU Watch Channel in your Telegram. You may also follow us on Twitter here and stay updated.)

Coal, lignite PSUs setting up 6 overburden processing plants: Govt

India likely to grow at 7.2% in FY'25: RBI Deputy Governor

Power Grid secures LoIs for Rs 11,326 crore transmission projects in Rajasthan

RITES marks ‘Swachhata Hi Seva’ campaign

SECL advances its digital push during Special Campaign 4.0